Bill of quantities of construction and installation works example. Drawing up a bill of quantities. General characteristics of the object


GOST 21.508-93

Group J01

INTERSTATE STANDARD

System of design documents for construction

RULES FOR THE IMPLEMENTATION OF WORKING DOCUMENTATION OF GENERAL PLANS OF ENTERPRISES, CONSTRUCTIONS AND HOUSING AND CIVIL OBJECTS

System of building design documents. Rules of fulfillment of working documentation of general layouts of enterprises, buildings and civil housing objects

ISS 01.110
OKSTU 0021

Introduction date 1994-09-01

Foreword

1 DEVELOPED by the Design Institute N 2 (PI-2), the Central Research and Design and Experimental Institute for Methodology, Organization, Economics and Design Automation (TsNIIproekt), the Promstroyproekt Design Institute, the Central Research and Design Institute for Urban Planning (TsNIIPUrban Construction)

INTRODUCED by Gosstroy of Russia

2 ADOPTED by the Interstate Scientific and Technical Commission for Standardization and Technical Regulation in Construction November 10, 1993

Voted for the adoption of the standard:

State name

Name of the public administration body for construction

The Republic of Azerbaijan

Gosstroy of the Republic of Azerbaijan

Republic of Armenia

State Architecture of the Republic of Armenia

Republic of Belarus

Gosstroy of the Republic of Belarus

The Republic of Kazakhstan

Ministry of Construction of the Republic of Kazakhstan

Republic of Kyrgyzstan

Gosstroy of the Kyrgyz Republic

the Russian Federation

Gosstroy of Russia

The Republic of Tajikistan

Gosstroy of the Republic of Tajikistan

Ministry of Construction and Architecture of Ukraine

3 INTRODUCED from September 1, 1994 as the state standard of the Russian Federation by Decree of the Gosstroy of Russia dated April 5, 1994 N 18-31

4 INSTEAD OF GOST 21.508-85

5 REVISION. March 2002


THE AMENDMENT IS MADE, published in IUS N 3, 2014

Amended by database manufacturer

1 area of ​​use

1 area of ​​use

This standard establishes the composition and rules for drawing up working documentation for master plans for enterprises, structures and housing and civil facilities * for various purposes (hereinafter referred to as master plans).
_____________________
* Microdistricts, quarters, groups of residential buildings and public buildings are considered hereinafter as residential and civil objects.

2 Normative references

________________

See note FSUE "STANDARTINFORM"


This standard uses references to the following standards:

GOST 2.303-68 Unified system for design documentation. lines

GOST 21.101-93 Design documentation system for construction. Basic requirements for working documentation

GOST 21.110-95 Design documentation system for construction. Rules for the implementation of the specification of equipment, products and materials

GOST 21.204-93 Design documentation system for construction. Conditional graphic designations and images of elements of master plans and transport facilities

GOST 21.510-83 Design documentation system for construction. Rules for the implementation of working drawings of railway tracks

GOST 21.511-83* System of design documentation for construction. Rules for the implementation of working drawings of roads
________________
* The document is not valid on the territory of the Russian Federation. GOST R 21.1701-97 applies, hereinafter in the text. - Database manufacturer's note.

3 General

3.1 The working documentation of master plans is carried out in accordance with the requirements of this standard, GOST 21.101 and other related standards of the design documentation system for construction (SPDS).

3.2 The composition of the working documentation of the master plan includes:

- working drawings of the general plan (the main set of working drawings of the GP brand. When combined in one main set of working drawings of the general plan and transport facilities, the main set of working drawings is assigned the GT brand);

- sketch drawings of general views of non-standard products, structures, devices and small architectural forms (hereinafter - sketch drawings of general views of non-standard products);

- statement of the need for materials - according to GOST 21.110 *;

- statement of volumes of construction and installation works - in accordance with GOST 21.110 *;
________________
* Performed if there are instructions in the contract for the performance of design work.

3.3 The composition of the main set of working drawings of the master plan includes:

- general data on working drawings;

- layout plan;

- relief organization plan;

- plan of earth masses;

- master plan of engineering networks;

- landscaping plan;

- remote elements (fragments, nodes) in accordance with GOST 21.101 *.
___________________
* Perform with high saturation of images.

3.4 Working drawings of the main set are performed on the engineering and topographic plan (except for the drawing of the earth mass plan).

It is allowed to carry out a layout plan, a master plan of engineering networks and a plan for landscaping the territory without drawing horizontal contours of the terrain.

3.5 The contours of the designed buildings and structures are applied to the plan according to architectural and construction working drawings, taking the coordination axes of buildings and structures aligned with the inner edges of the walls.

When the distance from the outer edge of the wall of the building, structures to the coordination axis on the image scale exceeds the thickness of the contour line, the latter is referred from the coordination axis to the corresponding distance () in accordance with Figure 1.

3.6 Plans of working drawings have the long side of the conditional border of the territory along the long side of the sheet, while the northern part of the territory should be at the top. North orientation deviation within 90° to the left or right is allowed. Plans located on different sheets are performed with the same orientation.

3.7 With low saturation of images, it is allowed to combine several different plans into one with the assignment of an appropriate name to it.

Example - "Layout plan and plan for organizing the relief", "Plan for organizing the relief and earth masses".

3.8 With a high saturation of the images of the landscaping plan, it is allowed to carry out several plans by type of work, assigning a corresponding name to each plan.

An example is "Plan of gardening", "Plan of arrangement of small architectural forms", "Plan of driveways, sidewalks, paths and platforms".

3.9 It is allowed to divide the plan into several sections, placing them on separate sheets. In this case, on each sheet where a section of the plan is shown, a diagram of the whole plan is given, broken down into sections, the numbers of the sheets on which they are placed are indicated, and the section shown on this sheet is indicated by hatching.

3.10 Working drawings of master plans are allowed to be produced in stages - by developments as the relevant working drawings of buildings, structures of the projected enterprise or housing and civil facility are completed.

In this case, each development is drawn up as of a certain date with the corresponding additions to the working drawings. The next development is not considered and is not formalized as a change.

Developments are assigned serial numbers.

3.11 During the next development, the main inscription is supplemented on the left with columns 10-13 in accordance with GOST 21.101 in accordance with Figure 2.

A list of drawing developments is placed above the main inscription: for the layout plan, plans for organizing the relief, earth masses and landscaping - in form 1, for the master plan of engineering networks - in form 2.

Examples of registration of development sheets are given in appendices A and B.

3.12 Images in the drawings of the general plan are performed by lines in accordance with GOST 2.303:

- solid thick main ones - the contours of the designed buildings and structures (except for buildings and structures on the plan of earth masses), the "red" line, the design horizontals with marks that are multiples of 0.50 and 1.00 m;

- dashed thin - lines of "zero" works and fracture of the design relief;

Dash-dotted very thick with two points - the conditional border of the territory of the projected enterprise, building, structure;

- solid thin - designed buildings, structures on the plan of earth masses and all other elements of the master plan.

3.13 Plans of working drawings are made on a scale of 1:500 or 1:1000, fragments of plans - on a scale of 1:200, nodes - on a scale of 1:20.

It is allowed to execute plans on a scale of 1:2000, nodes - on a scale of 1:10.

The scale of the image is indicated in the main inscription after the name of the image.

If several images are placed on the sheet, made at different scales, then the scales indicate the drawing field under the name of each image.

3.14 The system of elevation marks adopted in the working drawings of general plans must correspond to the system of elevation marks adopted on the engineering and topographic plan.

3.15 Dimensions, coordinates and height marks are indicated in meters with an accuracy of two decimal places.

3.16 The value of the angles is indicated in degrees with an accuracy of one minute, and if necessary - up to one second.

3.17 The magnitude of the slopes is indicated in ppm without indicating the unit of measurement.

The steepness of the slopes is indicated as the ratio of the unit height of the slope to the horizontal position.

3.18 The main conventional graphic symbols and images of the elements of the master plan and transport facilities are accepted in accordance with GOST 21.204.

Small architectural forms (for example, gazebos, awnings, fountains, sculptures, pergolas, etc.) and other structures, products, devices (for example, benches, urns, etc.) are performed in a simplified manner on the scale of the drawing or with conventional graphic symbols.

3.19 When performing the working drawings of the master plan, the serial numbers of buildings and structures (including fences, retaining walls, flyovers, galleries, tunnels) are usually taken according to the master plan developed at the previous design stages.

Drainage structures (ditches, trays, pipes) are assigned independent serial numbers.

When combined in one main set of master plan drawings and transport facilities, railways and roads are assigned independent serial numbers.

It is allowed not to assign serial numbers to roads and drainage facilities. In this case, their coordinates are indicated on the plan.

3.20 On the plans (except for the earth mass plan), an explication of buildings and structures is given in form 3 (for master plans for industrial enterprises) or a list of residential and public buildings and structures in form 4 (for master plans of housing and civil facilities). It is allowed to give an explication or a list of buildings and structures on a sheet of general data on working drawings.

3.21 In the columns of the explication of buildings and structures indicate:



- in the column "Name" - the name of the building, structure;

- in the column "Grid square coordinates" - the coordinates of the lower left corner of the building geodetic grid square, within which its number is applied on the image of the building and structure (if necessary).

An example of the design of the explication of buildings and structures is given in Appendix B.

3.22 In the columns of the statement of residential and public buildings and structures indicate:

- in the column "Number on the plan" - the number of the building, structure;

- in the column "Name and designation" - the name of the building, structure, indicating the designation of an individual or standard project, project according to the catalog;

- in other columns - data in accordance with their names.

An example of registration of a statement of residential and public buildings and structures is given in Appendix D.

4 General data on working drawings

General data on working drawings are performed in accordance with GOST 21.101, taking into account the following changes and additions:

- specification sheet is not fulfilled;

- in general instructions, in addition to the information provided for by GOST 21.101, they give the designations and names of the documents that are the basis for the development of working drawings of the master plan (for example, materials for engineering and geodesic and engineering and geological surveys), the adopted system of coordinates and elevations.

5 Layout plan

5.1 On the layout plan (plan of the location of buildings and structures) put and indicate:

a) a construction geodetic grid or a marking basis replacing it, and for residential and civil objects, in addition, an urban geodetic grid, which should cover the entire plan;

b) the "red" line separating the territory of the highway, street, driveway and square from the territory intended for development;

c) fences with gates and gates or a conditional border of the territory. If the fence coincides with the "red" line or with the conditional border of the territory, then only the fence is applied with the corresponding explanation on the drawing;

d) wells and pits of engineering and geological surveys not indicated on the engineering and topographic plan;

e) buildings and structures, incl. communication (overpasses, tunnels);

f) production and storage sites;

g) motor roads and paved areas;

i) railway tracks;

j) landscaping elements (sidewalks, sports and recreation grounds);

k) elements and structures of the planning relief (slopes, retaining walls, ramps);

m) drainage facilities;

m) direction indicator to the north with an arrow with the letter "C" at the tip (in the upper left corner of the sheet).

5.2 The layout plan is carried out with a coordinate or dimensional reference.

5.3 The construction geodetic grid is applied to the entire layout plan in the form of squares with sides of 10 cm.

The origin of coordinates is taken in the lower left corner of the sheet.

The axes of the construction geodetic grid are indicated by Arabic numerals corresponding to the number of hundreds of meters from the origin, and in capital letters of the Russian alphabet.

Examples

1 0A (origin of coordinates); 1A; 2A; 3A - horizontal axes;

2 0B (origin); 1B; 2B; 3B - vertical axes.

In the drawings, performed on a scale of 1:500, the axes of the building geodetic grid are designated in accordance with the examples given.

Examples

1 0A (origin of coordinates); 0A+50; 1A; 1A+50; 2A; 2A+50 - horizontal axes;

2 0B (origin); 0B+50; 1B; 1B+50; 2B; 2B+50 - vertical axes.

It is allowed, if necessary, to use negative values ​​of the axes of the construction geodetic grid.

Examples

1 0A (origin of coordinates); 0A-50; -1A; -1A-50; -2A; -2A-50 - horizontal axes;

2 0B (origin); 0B-50; -1B; -1B-50; -2B; -2B-50 - vertical axes.

During the expansion, reconstruction and technical re-equipment of existing enterprises, it is allowed to retain the previously adopted designations of the axes of the construction geodetic grid.

5.4 Dimensional binding is carried out from the layout basis.

The staking basis can be any straight line passing through two points fixed on the ground, which are denoted by capital letters of the Russian alphabet.

Example - A; B.

5.5 Buildings and structures on the plan are applied to the scale of the drawing, indicating the openings of the gates and doors, the extreme axes and, if necessary, the coordinates of the axes of the gate or the binding of the gate to the coordination axes of the building.

5.6 Inside the contour of the building (structure) indicate:

a) the number of the building, structure in the lower right corner;

b) an absolute mark corresponding to the conditional zero mark adopted in the construction working drawings of a building, structure, which is placed on the shelf of the leader line and marked with a sign (for residential and civil facilities - if necessary).

5.7 On the contour of the building, structures indicate:

a) the coordinates of the points of intersection of the coordination axes of the building, structure in its two opposite corners, and in case of a complex configuration of the building, structure or its location not parallel to the axes of the building geodetic grid - in all corners, for centric structures - the coordinates of the center and one characteristic point, as well as diameter, for linear structures - the coordinate of the axis or the coordinates of the beginning and end of individual sections;

b) dimensional binding of the coordination axes of the building, structure to the alignment basis and the dimensions of the building, structure between the axes in the absence of a building geodetic grid;

c) designation of the coordination axes of the building, structure at coordinated points.

5.8 Around the contour of the building, structures show the blind area and entrance ramps, external stairs and platforms at the entrances.

5.9 On the layout plan, in terms of roads, they put and indicate:

a) crossing the railroad tracks;

b) road junctions;

c) coordinates or bindings of axes of highways and, if necessary, their numbers;

d) the width of roads;

e) radii of curves along the edge of the carriageway of motor roads at the places of their mutual intersection and junction;

f) slopes of embankments and cuts (if necessary).

5.10 In the absence of the main set of working drawings of highways (grade AD), the layout plan is carried out taking into account the requirements of GOST 21.511.

5.11 On the layout plan, in the part of the railway tracks, they put and indicate:

a) track number;

b) turnouts;

c) stops;

d) slopes of embankments and excavations (if necessary).

5.12 In the absence of the main set of working drawings of railway tracks (PZH brand), the layout plan is carried out taking into account the requirements of GOST 21.510. At the same time, the bottom marks and the magnitude of the slopes of the drainage structures and the slope indicators do not indicate.

5.13 On the breakdown plan, a list of drainage facilities is given in form 5.

An example of a statement of drainage facilities is given in Appendix D.

5.14 An example of drawing up a layout plan of a production enterprise with a coordinate reference is given in Appendix E.

6 Terrain plan

6.1 The relief organization plan is carried out on the basis of a layout plan without indicating and drawing the coordination axes of buildings and structures, coordinates, sizes and dimensional references.

6.2 On the relief organization plan, apply and indicate:

a) absolute marks inside the contour of buildings and structures, in accordance with 5.6 (listing b);

b) design marks and slope indicators along the "red" lines;

c) design horizontals or design marks of the reference points of the layout, indicating the direction of the slope of the design relief;

d) marks of the bottom and top of slopes, stairs, retaining walls, ramps;

e) bottom marks in the places of fractures of the longitudinal profile, the direction and magnitude of the slopes of the drainage structures;

f) storm water gratings at low points of the design relief with marks of the tops of the gratings;

g) design marks of the layout and actual marks of the terrain along the outer contour of the blind area in the corners of buildings and structures or, in the absence of a blind area, the indicated marks at the intersection of the outer faces of the walls with the relief at the corners of buildings and structures - in the form of a fraction with a design mark in the numerator and actual - in the denominator;

i) design marks of the layout and actual marks of the terrain (if necessary) along the top of sites for various purposes at the intersection of their edges with the relief at the corners and at characteristic points;

j) fracture lines of the design relief - when the plan is implemented at the design marks of the reference points of the layout;

k) the direction of the slope of the design relief with berghash - when the plan is implemented in the design horizontals and arrows - when the plan is implemented in the design elevations.

6.3 On the relief organization plan, in terms of roads, put and indicate:

a) design horizontals - when implementing the plan in design horizontals;

b) the contours of the transverse profile of highways - when the plan is implemented at design elevations;

c) fracture points of the longitudinal profile with design marks;

d) slope indicators along the axis of the carriageway of motor roads;

e) drainage structures - ditches, trays with bottom marks in places of fractures of the longitudinal profile and the magnitude of the slopes of the bottom of the structures;

f) storm water gratings at lower points of the longitudinal profile with marks of the tops of the gratings.

6.4 On the relief organization plan, in terms of railway tracks, put and indicate:

a) directional indicators;

b) marks of the bottom of the drainage structures in the places of fractures of the longitudinal profile and the values ​​of the slopes of the bottom of the structures.

6.5 The relief organization plan should, as a rule, be carried out in the design horizontals.

6.6 When implementing the plan for organizing the relief in the design horizontals, they are carried out with a cross section of the relief through 0.10 or 0.20 m throughout the planned territory (ground surface, roads, sites). It is allowed to apply design contours with a relief section every 0.50 m in areas with a uniform slope of the relief.

The marks of the design contours are inscribed from the side of the elevation of the relief. Elevations of design horizontals, multiples of 1.00 m, are indicated in full, intermediate ones are given as an integer corresponding to two decimal places.

6.7 When implementing the plan for organizing the relief in the design marks of the reference points of the layout, as a rule, the following are taken as reference points:

a) corners of buildings, structures and sites;

b) elevated and lowered points of the design relief;

c) crossing the axes of highways;

d) fracture points of the longitudinal profile of roads and railways.

6.8 On the relief organization plan indicate the design marks of the entrance and exit along the bottom of pipes and intersleeper trays, as well as marks of turning points along the bottom of drainage ditches and trays. On the shelf of the leader line of drainage ditches and trays, their abbreviated name is given.

Examples

1 D.l. - the bottom of the tray;

2 D.k. - the bottom of the ditch.

6.9 Examples of drawing up plans for organizing the relief in the design horizontals and design marks of the reference points of the layout are given in Appendices G and I, respectively.

7 Earth mass plan

7.1 Calculation of volumes of earthen masses is performed, as a rule, by the method of squares.

It is allowed to carry out the earth mass plan using other methods. The content and form of the plan is determined by the method of calculating the volume of earthen masses and the conditions for the production of work.

7.2 On the plan of earth masses apply and indicate:

a) a construction geodetic grid or a marking basis replacing it;

b) a grid of squares for calculating the volume of earth masses with design, actual and working marks in the corners of the squares, a line of "zero" work with the allocation of the area of ​​excavations by hatching at an angle of 45 ° to the base of the grid and indicating the volume of earth masses within each square or other figure, formed by the contour of the layout;

c) buildings and structures;

d) fencing or conditional border of the territory;

e) slopes, retaining walls.

7.3 The grid of squares, as a rule, is inscribed in the construction geodetic grid, taking the side of the square equal to 20 m. m, depending on the nature of the relief and ensuring the required accuracy of calculating the volume of earth masses.

It is allowed, depending on the configuration of the planned territory, to calculate the volume of earth masses using figures other than a square. In these cases, the dimensions of the figures are indicated on the drawing.

7.4 Under each column of squares of the plan of earth masses, a table is given in form 6, in the corresponding columns of which the total volumes of embankment and excavation are indicated in the column of squares, and in the lines of the total volumes on the right - the total volumes of embankment and excavation throughout the planned territory.

7.5 In case of occurrence within the planned territory of soils to be removed (fertile soil layer, peat, soil unsuitable as the foundation of buildings, structures), before the development of an earth mass plan for the entire territory, a plan for the removal of soils within the contour of the occurrence of soils to be removed is carried out , making it similar to the plan of earth masses.

On the soil removal plan, the design marks are taken to be the bottom marks of the soil to be removed, which, when the earth mass plan is subsequently executed, are considered as actual marks.

If there are heterogeneous soils on the construction site, it is allowed to carry out plans for each type of soil, assigning the appropriate name to the drawing.

Examples

1 "Plan of earthen masses. Removal of construction debris";

2 "Plan of earthen masses. Development of rocky soils".

In the case of occurrence of soils to be removed by a layer of the same thickness, the soil removal plan may not be implemented. At the same time, the marks of the bottom of the soils to be removed are taken as the actual marks for the plan of earth masses, and the calculated volume of the removed soils is entered in the corresponding lines and columns of the statement in form 7.

7.6 On the plan of earthen masses lead:

a) statement of volumes of earthen masses in form 7;

b) text instructions on the need to adjust the working marks in the places of lawns, troughs under the clothes of roads, platforms and the upper structure of the railway tracks.

7.7 Examples of drawing up a plan of earth masses and a statement of volumes of earth masses are given in Appendices K and L, respectively. Examples are developed for the case of vertical planning before the construction of buildings and structures.

8 Master plan of engineering networks

8.1 The master plan of engineering networks is performed on the basis of the layout plan, but without absolute marks of buildings, structures, gate bindings and designation of the coordination axes of buildings, structures.

If necessary, the outer contours of the soles of the foundations of the designed and existing buildings and structures are applied on the plan.

On the images of roads and railways, only the coordinates or bindings of their axes are indicated.

Engineering networks are performed by conventional graphic symbols in accordance with GOST 21.204.

8.2 On the master plan of engineering networks, apply and indicate:

a) communication facilities for laying networks;

b) underground, ground and overground networks;

c) storm water gratings, supports and racks of communication structures.

8.3 Engineering networks are applied according to the working drawings of the corresponding main sets with coordinate or linear reference of the network axis in each characteristic area, with the image of compensators, niches, wells, chambers and indicating their designations.

8.4 An example of a master plan for engineering networks is given in Appendix M.

9 Landscaping plan

9.1 The plan for the improvement of the territory is carried out on the basis of a layout plan without specifying the coordination axes, coordinates and dimensional references, absolute marks of buildings and structures.

On the images of roads and railways, if necessary, only the coordinates or references of their axes are indicated.

9.2 On the landscaping plan, the following is applied and indicated:

a) sidewalks, paths and their width;

b) sites for various purposes and their sizes;

c) small architectural forms and portable products of recreation areas;

d) trees, shrubs, flower beds, lawns.

9.3 Improvement elements are tied to the outer edges of the walls of buildings, structures, "red" lines, roads or railways.

For an ordinary planting of trees and shrubs, a dimensional binding of a row is given.

9.4 With a complex configuration of paths, when trees and shrubs are located in free groups, it is allowed, instead of dimensional reference, to apply an auxiliary grid of squares with sides equal to 5-10 m in the areas of their location, with its binding to the construction geodetic grid, marking base, buildings, structures, automobile roads and railways.

9.5 Improvement elements are assigned positional designations. Positional designations of small architectural forms and portable products are indicated on the leader line in circles with a diameter of 6 mm. The designation of landscaping elements is indicated on the leader line in circles with a diameter of 8-12 mm in the form of a fraction: in the numerator - the positional designation of the species or type of planting, in the denominator - their number or area (for flower beds).

9.6 On the plan for the improvement of the territory lead:

a) a list of small architectural forms and portable products in form 8, an example of which is given in Appendix H;

b) a list of landscaping elements in form 9, an example of which is given in Appendix P;

c) a list of sidewalks, paths and platforms in form 10, an example of which is given in Appendix P; (Figure R.1);

d) sections, sections and knots of sidewalks, paths and platforms. An example of the design of sections of sidewalks, paths and platforms is given in Appendix C;

e) a list of roads, entrances and driveways in accordance with GOST 21.511 (form 1) - for residential and civil facilities, an example of which is given in Appendix R (Figure R.2);

f) relevant textual instructions, for example, on the conditions for planting trees and shrubs, arranging flower beds and lawns, etc.

9.7 It is allowed to place the statements specified in 9.6 on a sheet of general data.

9.8 Examples of the design of an improvement plan, completed by type of work, are given: in Appendix T - "Greening Plan"; in Appendix Y - "Plan of the location of small architectural forms and portable products"; in Appendix F - "Plan of driveways, sidewalks, paths, sites."

10 Sketch drawings of general views of non-standard products

10.1 A draft drawing defines the design of a non-standard product, contains a simplified image, basic parameters and technical requirements for the product in the amount of initial data (building) necessary for the development of design documentation.

10.2 Sketch drawings are developed for products (structures, devices) in the absence of their mass production, standard drawings (documentation for mass use), standards or other documents for these products.

10.3 For each non-standard product, a separate sketch drawing is made. The exception is a group of products that have common design features, for which it is allowed to perform a group sketch drawing.

10.4 The sketch drawing is assigned an independent designation, consisting of the designation of the main set of working drawings in accordance with GOST 21.101, through the cipher point H and the serial number of the sketch drawing.

Example - 2345-11-GP.N1; 2345-11-GP.N2.

Note - the distance from the inner edge of the contour of the building, structure to the coordination axis

Picture 1

Figure 2

Form 1

Drawing development sheet

Statement of developments of the master plan of engineering networks

Form 3

Explication of buildings and structures

List of residential and public buildings and structures

List of drainage facilities

To the plan of earth masses

graph width; - number of graphs

Note - The width and number of columns and their number must correspond to the grid of squares of the earth mass plan.

Form 7

Statement of volumes of earth masses

Notes

2 The second line of the table head is provided for the name of the territory for which the data is given.


An example is "Pre-factory territory", "Residential development". The number of allocated parts of the territory is specified according to the design data.

List of small architectural forms and portable products

Form 9

List of landscaping elements

Form 10

List of sidewalks, paths and platforms

Annex A (informative). An example of a drawing development sheet

Annex A
(reference)

An example of a drawing development sheet

Appendix B (informative). An example of a statement of development of a master plan for engineering networks

Annex B
(reference)

An example of a statement of development of a master plan for engineering networks

Note - An example of the design of the statement is given for the coordinate referencing of networks.

Annex B (informative). An example of the design of the explication of buildings and structures

Annex B
(reference)

An example of the design of the explication of buildings and structures

Annex D (informative) An example of registration of a statement of residential and public buildings and structures

Annex D (informative) An example of a statement of drainage facilities

Annex E (informative) An example of a layout layout

Annex G (informative) An example of the design of a relief organization plan in the design horizontals

Annex I (informative) An example of the design of a relief organization plan in design elevations

Appendix K (informative) Example of drawing up a plan of earth masses

Annex L (reference) An example of registration of a statement of volumes of earth masses

Soil name

Quantity, m

Note

factory area

pre-factory territory

Mound (+)

Notch (-)

Mound (+)

Notch (-)

1 Territory planning ground

2 displaced soil,

including on device:

a) underground parts of buildings and structures

b) road surfaces

c) railway ways

d) underground networks

e) drainage facilities

f) fertile soil in landscaping areas

3 Soil for the construction of high floors of buildings and embankments of structures

4 Compaction correction

Eng.-Geol. sophistication.

Total suitable soil

5 Lack of suitable soil

6 Soil not suitable for embankment of foundations of buildings, structures and subject to removal from the territory (peat)

7 Fertile soil, total, including:

a) used for landscaping

b) excess fertile soil (land reclamation)

8 Total processed soil

*Including preliminary cutting of fertile soil.

** In a career.

*** In the dump.

(Amendment. IUS N 3-2014).

Annex M (reference) An example of a master plan for engineering networks

Annex H (informative) Example of registration of a statement of small architectural forms and portable products

Annex P (informative) Example of registration of a list of landscaping elements

Annex P (informative) An example of registration of a list of sidewalks, paths and platforms; An example of registration of a statement of roads, entrances and driveways

Annex R
(reference)

An example of registration of a list of sidewalks, paths and platforms

Figure P.1

An example of registration of a statement of roads, entrances and driveways

Figure P.2

Annex C (informative) An example of the design of sections of sidewalks, paths and platforms

Annex T (informative). An example of a landscaping plan

Appendix T
(reference)

An example of a landscaping plan

Appendix Y (reference) An example of a layout plan for the location of small architectural forms and portable products

Appendix F (informative) An example of a plan for driveways, sidewalks, paths, platforms

NOTE FSUE "STANDARTINFORM"

GOST 21.101-93 was replaced by GOST 21.101-97 Basic requirements for design and working documentation;

GOST 21.510-83 has been replaced by GOST R 21.1702-96 Project documentation system for construction. Rules for the implementation of working documentation for railway tracks (valid only on the territory of the Russian Federation);

GOST 21.511-83 has been replaced by GOST R 21.1701-97 Project documentation system for construction. Rules for the implementation of working documentation for highways (valid only on the territory of the Russian Federation)

Electronic text of the document
prepared by Kodeks JSC and verified against:
official publication
M.: Standartinform, 2008
(as of March 2008)

Revision of the document, taking into account
changes and additions prepared
JSC "Kodeks"

For the construction of foundations, trenches are torn off. The excavation of trenches is carried out using a single-bucket backhoe. The division into grips is shown in the drawing. The volume of mechanized earthworks is equal to the volume of excavated soil.

The bottom of the trenches is cleaned with a bulldozer to a depth of 10 cm. The width and length of the trench is equal to the dimensions of the building plus 0.5 meters.

Installation of load-bearing structures. The breakdown into grips is shown in the drawing.

When installing a wall fence, the end and longitudinal walls are taken as a grip.

The roof structure is adopted with coating vapor barrier, cement screed and a three-layer roofing felt carpet. The breakdown into grips is similar to the breakdown during the installation of the supporting structures of the frame.

The floor area is conventionally assumed to be equal to the built-up area of ​​the building.

The area of ​​window openings is taken from the calculation of a continuous strip.

The area of ​​lime painting is equal to the area of ​​partitions and walls along the entire perimeter to a height of 2 m.

The duration of electrical, plumbing, installation of technological equipment and landscaping is determined as a percentage of the cost of construction and installation work.

Construction area of ​​the object:

Building volume:

Costs:

construction and installation works (at the rate of 15 rubles per 1 m 3):

installation of plumbing equipment:

electrical work:

landscaping work:

Table 2. Bill of quantities

p.p.

Name of works

Unit ism.

Scope of work on grips

Total

Site preparation

Cutting the vegetation layer

Excavation with an excavator

Erasure

Backfilling

Soil compaction

Formwork installation

Rebar laying

Foundation concreting

Formwork removal

Unloading reinforced concrete columns to the warehouse

Installation of columns

Unloading farms to the warehouse

Truss installation

Unloading floor slabs to the warehouse

Installation of floor slabs

Unloading run-beams to the warehouse

Installation of run-beams

Unloading wall panels to the warehouse

1.2*6m

Installation of wall panels

1.2*6m

Brick unloading

Brick wall construction

Installation of window frames

Glazing

Substrate preparation for concrete flooring

Pouring concrete floor

Linoleum floor installation

vapor barrier

Warming

Cement screed roof

Roll roofing

Truss welding

Coating plate welding

Wall panel welding

Sealing of foundation cups with concrete on fine aggregate

Concreting of foundation cups

Filling the joints of wall panels with cement. sand rast.

Continuation of Table 2

Filling of seams of plates of a covering tsem. sand rast.

wall painting

Whitewash

Plumbing installation

Electrician

landscaping

Unrecorded works

6.2 List of determination of the labor intensity of work and the need for machines and mechanisms

The normative base for calculating labor costs is the HPES and TEP, according to which we determine the time standards for each type of work. Labor costs for works, the volumes of which are measured in natural units, are determined by multiplying the norm of time by the volume of work. Labor costs for works, the volumes of which are given in value terms - rubles, are determined by dividing the volume of work by the average value of output per person per day

Norm of time, the time set for the manufacture of a unit of production or the performance of a certain amount of work by one or a group of workers of appropriate qualifications in certain organizational and technical conditions. The norm of time is calculated in man-hours or man-days. The rate of time is inversely proportional to the rate of output.

Production rate, the number of units of production (or work) that must be manufactured (performed) per unit of time (hour, shift, month) in certain organizational and technical conditions by one or a group of workers of the appropriate qualification. The output rate, depending on the type of work, can be expressed in pieces, units of measure of length, area, volume or weight.

Labor costs- this is the amount of time required by one person to perform a certain type of work (person / hour, person / day).

Labor intensity is the time spent on the production of a unit of output. In other words, labor intensity is the sum of labor costs.

All documents presented in the catalog are not their official publication and are intended for informational purposes only. Electronic copies of these documents can be distributed without any restrictions. You can post information from this site on any other site.

GOST 21.101-93

INTERSTATE STANDARD

SYSTEM OF DESIGN DOCUMENTS FOR CONSTRUCTION

PRIMARY REQUIREMENTS
TO WORKING DOCUMENTATION

INTERSTATE SCIENTIFIC AND TECHNICAL COMMISSION
FOR STANDARDIZATION AND TECHNICAL REGULATION
IN CONSTRUCTION (MNTKS)

Foreword

INTRODUCED by the Ministry of Construction of Russia

2 ADOPTED by the Interstate Scientific and Technical Commission for Standardization and Technical Regulation in Construction November 10, 1993

State name

Name of the public administration body for construction

The Republic of Azerbaijan

Gosstroy of the Republic of Azerbaijan

Republic of Armenia

State supraarchitectures of the Republic of Armenia

Republic of Belarus

Gosstroy of the Republic of Belarus

The Republic of Kazakhstan

Ministry of Construction of the Republic of Kazakhstan

Republic of Kyrgyzstan

Gosstroy of the Kyrgyz Republic

The Republic of Moldova

Ministry of Architecture of the Republic of Moldova

The Russian Federation

Gosstroy of Russia

The Republic of Tajikistan

Gosstroy of the Republic of Tajikistan

Ukraine

Ministry of Construction and Architecture of Ukraine

3 INTRODUCED from September 1, 1994 as the state standard of the Russian Federation by Decree of the Ministry of Construction of Russia dated August 12, 1994 No. 18-12

3) equipment specifications in accordance with GOST 21.110;

4) statements and summary statements of the need for materials in accordance with GOST 21.110 *;

5) statements and collections of statements of volumes of construction and installation works in accordance with GOST 21.110 *;

6) other documentation provided by the relevant standards of the Design Documentation System for Construction (SPDS);

7) estimate documentation according to the established forms *.

* Perform if necessary.

2. BASIC REQUIREMENTS FOR DESIGN DRAWINGS INTENDED FOR CONSTRUCTION AND INSTALLATION WORKS

2.1. Working drawings intended for the production of construction and installation works are combined into sets (hereinafter referred to as the main sets) by brand in accordance with the appendix.

2.2. The main set of working drawings of any brand can be divided into several main sets of the same brand according to any feature with the addition of a serial number to it.

EXAMPLES: AC1; AC2; QOL1; QOL2.

2.3. Each main set of working drawings is assigned a designation, which includes the basic designation ** and, through a hyphen, the brand of the main set.

** Before the release of the corresponding classifier, the basic designation is assigned according to the system in force in the organization.

2.4. The composition of the main sets of working drawings includes general data on working drawings, drawings and diagrams provided for by the relevant standards of SPDS.

2.5. General data on working drawings

2.5.1. On the first sheets of each main set of working drawings, general data on working drawings are given, including:

1) a list of working drawings of the main set in the form;

2) a list of reference and attached documents in the form;

3) a list of the main sets of working drawings in the form;

4) a list of specifications (if there are several specifications for layouts in this main set) in the form;

5) symbols that are not established by state standards and the meanings of which are not indicated on other sheets of the main set of working drawings;

6) general instructions;

7) other data provided by the relevant SPDS standards.

STATEMENT OF WORKING DRAWINGS OF THE MAIN SET

SPECIFICATIONS LIST


Instructions on filling out the list of working drawings of the main set

In the statement of working drawings of the main set indicate:

1) in the column "Sheet" - the serial number of the sheet of the main set of working drawings;

2) in the column "Name" - the name of the images placed on the sheet, in full accordance with the names given in the main inscription of the corresponding sheet;

3) in the column "Note" - additional information, for example, about changes made to the working drawings of the main set.

Instructions for Completing the Specification Sheet

The specification sheet indicates:

1) in the column "Sheet" - the number of the sheet of the main set of working drawings, on which the specification is placed;

2) in the column "Name" - the name of the specification in full accordance with its name indicated on the drawing;

3) in the column "Note" - additional information, incl. about changes to the specifications.

STATEMENT OF MAIN SETS OF WORKING DRAWINGS.
LIST OF REFERENCES AND APPLIED DOCUMENTS


Instructions on filling out the statement of the main sets of working drawings

In the statement of the main sets of working drawings indicate:

1) in the column "Designation" - the designation of the main set of working drawings and, if necessary, the name or distinctive index of the organization that issued the document;

2) in the column "Name" - the name of the main set of working drawings;

3) in the column "Note" - additional information, incl. on changes in the composition of the main sets of working drawings.

Instructions for completing the list of reference and attached documents

In the statement of reference and attached documents indicate:

1) in the column "Designation" - the designation of the document and, if necessary, the name or distinctive index of the organization that issued the document;

2) in the column "Name" - the name of the document in full accordance with the name indicated on the title page or in the main inscription;

3) in the column "Note" - additional information, incl. on changes to applicable documents.

APPENDIX 3
Mandatory

LIST OF ESKD STANDARDS, THE REQUIREMENTS OF WHICH DO NOT CONTRACT THE STANDARDS OF SPDS AND ARE TO BE TAKEN INTO ACCOUNT WHEN IMPLEMENTING PROJECT DOCUMENTATION FOR CONSTRUCTION

Designation and name of the standard

Conditions for applying the standard

Full name

Reduction

Director

Dir.*

Chief Engineer

Ch. engineer*

The chief architect of the project

GAP*

Chief Project Engineer

GUI*

Chief Specialist

Ch. specialist.*

manager

Head*

Architect

Arch.*

Engineer (I, II, III category)

Eng. (I, II, III cat.)*

Technician

Tech.*

Institute

Institute*

Workshop (in design institutes)

Mast.*

Group

Gr.

Release

issue

Chapter

sec.

Anti-seismic seam

a.s.l.

Expansion joint

d.sh .

Temperature joint

t.sh.

mark

elev.

Ground level

ur.z.

Rail head level

ur.g.r.

Clean floor level

ur.n.p.

Plot

account*

Document

doc*

* Abbreviations are used only in the title block.

APPENDIX 5
Mandatory

The main inscription and additional columns to it on the sheets of the main set of working drawings


The main inscription and additional columns to it for drawings of building products (first sheet)


The main inscription and additional columns to it for text documents (first sheet)


The main inscription and additional columns to it for drawings of building products and text documents (subsequent sheets)


Instructions on filling in the main inscription and additional columns to it

In the columns of the main inscription and additional columns to it (the numbers of the columns on the forms are shown in brackets) indicate:

1) in column 1 - the designation of the document (the main set of working drawings, product drawing, text document, etc.);

2) in column 2 - the name of the enterprise (including institutions and service enterprises), which includes the building (construction), or the name of the microdistrict;

3) in column 3 - name of the building (structure);

4) in column 4 - the name of the images placed on this sheet, in exact accordance with the names of the images in the drawing.

The names of specifications and other tables, as well as textual indications related to images, are not indicated in the column;

5) in column 5 - the name of the product and / or the name of the document;

6) in column 6 - the symbol of the stage "Working documentation" - "P";

7) in column 7 - the serial number of the sheet (pages of a text document for duplex printing). On documents consisting of one sheet, the column is not filled out;

8) in column 8 - the total number of sheets of the document.

The column is filled out only on the first sheet. On the first sheet of a text document for duplex printing indicate the total number of pages;

9) in column 9 - the name or distinctive index of the organization that developed the document;

10) in column 10 - the nature of the work (developed, checked, normative control, approved); it is allowed to fill in free lines at the discretion of the developer with the positions of persons responsible for the release of the document (chief engineer (architect) of the project, head of department, chief specialist, etc.);

11) in columns 11-13 - the names and signatures of the persons indicated in column 10, and the date of signing.

If it is necessary to coordinate the document, then the signatures of the officials who approve the document are placed on the field for filing the sheet;

12) columns 14-19 - columns of the table of changes, which are filled in in accordance with clause;

13) column 20 - inventory number of the original;

14) column 21 - the signature of the person who accepted the original for storage, and the date of acceptance (day, month, year);

15) column 22 - the inventory number of the original document, in exchange for which the original was issued;

16) column 23 - designation of the material of the part (the column is filled out only on the drawings of the parts);

17) column 24 - the mass of the product shown in the drawing, in kilograms without indicating the unit of measurement. It is allowed to indicate the mass in other units of measurement, indicating them.

EXAMPLE: 2.4 t;

To form a matrix of initial data and draw up a schedule, the following calculations and reasoning were performed.

From the design data, we are given the construction period of the facility, which is 26 months or 572 days.

Selection of the nomenclature of work and the formation of flows.

Above-ground works include general construction and special construction works. The formation of the work processes of the above-ground cycle was carried out taking into account the recommendations for the choice of the range of works and the formation of works on modeling the organizational and technological scheme and is given in Table 3.1. From the total labor intensity, the values ​​of those works that are carried out outside the flow should be subtracted:

Out of flow:

Installation of equipment 1543 man-days

Commissioning of communications 257 man-days

Unrecorded work 1928 man-days

Start-up and adjustment works 185 man-days

Σ= 3913 man-days

In stream: 20881-3913=16968 man-days

As a result of calculating the network model, a critical construction period of 514 days was obtained.

T cr =514 days

T d = 572 days

∆Т=572-514=58 days

K - reserve time

K=58/572*І00=11%

The total reserve time for construction is 11% of the design period, which corresponds to the allowable 15-20%. The criterion of flow duration is the most important one. since the duration has an impact on the efficiency of construction, in this case, due to the reduction of the work period, it is possible to increase the efficiency and quality of construction. As you know, any time adjustments lead to a change in the financing of the facility under construction. therefore, in this work, their application is envisaged.

Applications application a

Table A.1

General characteristics of the object

Table A.2

Specification of prefabricated elements, maximum weight and dimensions of elements, ton / meter

Name of elements

Har-ka, tons / meter

Foundation blocks for walls

Foundation blocks for columns

Basement wall blocks

External wall panels

Wall panels internal

Reinforced concrete columns

Crossbars and beams

floor slabs

Stair flights and landings

Coating slabs

Lift shaft blocks

Ventilation blocks

Garbage chute pipes

Login elements

Table A.3

Bill of volumes of construction and installation works

Name of works

Unit rev.

Qty

Excavation

Mechanized earthworks for digging pits and trenches with removal of excess soil

Soil selection manually

Backfilling

Foundations

Installation of foundation blocks under the walls

Installation of foundation blocks for columns

Basement device

Installation of basement wall blocks

Underground waterproofing

Basement finishing (plastering, wall and ceiling painting)

Installation of structures

Installation of reinforced concrete structures:

Flights of stairs and landings in the basement

Crossbars and beams

Panel mounting

outdoor

Internal

Installation of large-panel partitions

floor slabs

Stair flights and platforms

Blocks of lift shafts

Volumetric blocks of sanitary cabins

ventilation blocks

Installation of floor slabs

Roofing (vapor barrier, insulation, cement screed)

Installation of garbage chute pipes

brickwork

Devices of brick partitions in 2 bricks

Devices of brick partitions in ½ brick

Devices of brick partitions in ½ brick in the basement

Floor preparation

Concrete preparation device for floors in the basement

Basement floor installation

Cement

Tiled

Soundproofing

Waterproofing

Plaster work

Wet plaster walls and ceilings

Filling windows and doorways

Hole filling:

Glazing of windows and stained-glass windows

oil painting

Oil painting on plaster and concrete

Wall cladding with ceramic tiles

Whitewashing and glue coloring

Adhesive wall painting

Ceiling whitewashing

Wall papering

Clean floor installation

Device

cement screed

Tiled floors

Linoleum flooring

Parquet floors

Arrangement of mezzanines and built-in wardrobes

m 2

Finishing work at the entrance

m 2

1. Complex earthworks.

Cutting the vegetation layer of the soil;

An excavation of a pit or trench will be swept up or loaded into dump trucks;

Transportation of soil by dump truck or bulldozer;

Cleaning the bottom of the pit manually;

The device of a sand cushion under the foundation (if necessary);

Backfilling.

2. Construction of monolithic reinforced concrete foundations.

Unloading and sorting of reinforcing meshes and formwork elements;

Pre-assembly of formwork panels;

formwork installation;

The same reinforcing bars, meshes and frames;

Welding works;

Supply of concrete mix;

Laying concrete mix;

Curing;

Formwork dismantling.

3. Construction of precast concrete foundations.

Installation of foundation blocks around the perimeter of the building;

The same wall blocks of the first row, second row, etc.;

The same landings and marches;

The same basement slabs.

4. Installation of the frame of a one-story industrial building.

Unloading and layout of structures;

Installation of columns in the glasses of foundations;

Concreting of the joints of columns in the glasses of foundations;

Enlarged assembly of farms (if necessary);

Installation of crane beams;

The same sub-rafter structures;

The same truss structures;

The same coating slabs;

Electric welding of assembly joints;

Concreting of joints of columns with crane beams, trusses;

Filling of seams of plates of a covering.

5. Installation of a typical floor made of monolithic reinforced concrete.

Unloading and sorting of reinforcing products and formwork panels;

Pre-assembly of formwork panels (if necessary);

Delivery of formwork to the place of installation;

The same reinforcing meshes and frames;

Welding works;

Supply of concrete mix;

Laying concrete mix;

Curing;

Formwork dismantling.

6. Installation of a typical precast concrete floor.

Unloading and other lifting and transport operations;

Installation of exterior wall panels;

The same internal;

The same partitions;

The same flights of stairs and landings;

The same sanitary cabins and ventilation blocks;

The same floor slabs, balcony slabs;

Welding works;

Sealing of seams of external and internal walls;

Filling the seams of floor slabs.

7. Roof device.

Preparation of the base of the roof (cleaning, drying, priming);

Supply of materials to the roof;

Vapor barrier device;

The same heater;

The same screeds;

Sticking of a rolled carpet;

Protective layer device;

The device of junctions.

8. Plastering surfaces.

Surface preparation;

Plastering (troweling) of joints between prefabricated floor panels;

Plastering walls;

Cutting corners;

Plastering window and door slopes.

Drawing up a bill of quantities.

After specifying the requirements for the completion of the preceding or preparatory processes and describing the technological sequence of operations, the scope of work should be determined.

When developing a technological map for the installation of structures made of monolithic or precast concrete, before compiling a bill of quantities, it is necessary to draw up a specification for monolithic reinforced concrete structures (Table 2.1) or a specification for mounting elements (Table 2.2), respectively.

Filling out the Specification for monolithic reinforced concrete structures should begin with the definition of all elements and structures that are related to the developed technological map according to the working drawings. Their list is entered in column 2. Columns 3, 4, 5, 6 and 8 are filled in on the basis of working drawings. The results of the product of columns 4, 5, 6 are entered in column 7. The total volume of concrete for all elements (column 9) is determined by the product of the values ​​in column 7 by the values ​​in column 8.

Table 2.1

Specification of monolithic reinforced concrete structures

Filling in the Specification of mounting elements is also carried out on the basis of the adopted architectural, planning and design solutions. Columns 2-8, 10 are filled in in accordance with the working drawings. Column 9 is filled in only for plate elements (walls, floor slabs, etc.) by multiplying the values ​​of column 4 by column 5. Columns 11 and 12 contain the results of multiplying the values ​​of column 7 by 10 and column 8 by 10, respectively.

Table 2.2

Specification of mounting elements

No. p / p Name of elements brand Dimensions, m Volume Cubic meters Weight, t Area sq.m Quantity, pcs. Volume of all elements Weight of all elements, t
Length Width Height (thickness)
1 foundation beam FB6-2 5,05 0,26 0,45 0,52 1,3 - 11,96 29,9
2 Extreme columns K96-1 0,4 0,4 10,5 1,68 4,2 - 36,96 92,4
3 Coating plate PG-1-4 0,3 1,16 2,9

The bill of quantities (Table 2.3) includes all the main and auxiliary processes that are performed in the designed complex construction process. The scope of work is determined using the specification of elements, as well as working drawings. Column 2 sequentially enters all the processes carried out in the production of the type of work for which the technological map is being developed. The units of measurement in column 3 must correspond to the enlarged meters given in the ENiR for this process. Next, column 5 is filled in with the calculation formulas, or, if the calculation was made earlier, indicating the place in the settlement and explanatory note. The results of the calculation are entered in column 4, taking into account the units of measurement given in column 3.

Editor's Choice
There is a belief that rhinoceros horn is a powerful biostimulant. It is believed that he can save from infertility ....

In view of the past feast of the holy Archangel Michael and all the incorporeal Heavenly Powers, I would like to talk about those Angels of God who ...

Quite often, many users wonder how to update Windows 7 for free and not incur trouble. Today we...

We are all afraid of judgment from others and want to learn not to pay attention to the opinions of others. We're afraid of being judged, oh...
07/02/2018 17,546 1 Igor Psychology and Society The word "snobbery" is quite rare in oral speech, unlike ...
To the release of the film "Mary Magdalene" on April 5, 2018. Mary Magdalene is one of the most mysterious personalities of the Gospel. The idea of ​​her...
Tweet There are programs as universal as the Swiss Army knife. The hero of my article is just such a "universal". His name is AVZ (Antivirus...
50 years ago, Alexei Leonov was the first in history to go into the airless space. Half a century ago, on March 18, 1965, a Soviet cosmonaut...
Don't lose. Subscribe and receive a link to the article in your email. It is considered a positive quality in ethics, in the system...